Pasminco Century Zinc Mine
Project Description
Century Zinc is the recently constructed $850 million open cut zinc mine located near Lawn Hill National Park in the north west of Queensland. A 1km cross country PLC controlled pipeline automatically transfers fuel to the Go Line refuelling facility. The facility has three refuelling bays to service the 23 Komatsu dump trucks, a 110kL day tank and two bulk lubricant storage tanks and an oily water separator. Five bulk lubricant tanks (from 5 - 55kL in size) and a waste oil tank are installed in a bund adjacent to the workshops. Each grade of oil is reticulated to hose reels at each of the five service bays. A large separator pit and oily water separator was installed to handle drainage from the Truckwash and the workshops.
TfA Contribution
TfA's role included detailed design and tender documentation, contract negotiations, site inspections, commissioning and user documentation of all diesel and oil distribution facilities and oily water treatment for the Go Line, Workshops and Truckwash.
Timing
Design and construction completed in seven months.
Value
Total project value for the facilities designed by TfA was $2.0 million.